Critical Path Method Cheat Sheet: Float, Dependencies and Scheduling Basics
Written by
The Cheat School Team
Published
October 22, 2026
Reading time
2 min read
Every construction schedule in MS Project or Primavera P6 is built on the Critical Path Method. Understand these terms and the software stops being confusing.
Key terms
| Term | Meaning |
|---|---|
| ES (early start) | Earliest an activity can begin |
| EF (early finish) | ES + duration |
| LS (late start) | Latest it can begin without delaying the project |
| LF (late finish) | Latest it can finish without delaying the project |
| Total float | LS minus ES (or LF minus EF) |
| Free float | Delay possible without delaying the next activity |
| Critical path | Chain of activities with zero total float |
How to calculate it
- List activities, durations and what each depends on.
- Forward pass: work left to right to find ES and EF for each activity.
- Backward pass: work right to left from the project end to find LF and LS.
- Compute float. Activities with zero float form the critical path.
The four dependency types
- Finish to Start (FS): B starts after A finishes. Example: formwork then concreting. The most common type.
- Start to Start (SS): B starts after A starts. Example: plastering can start once brickwork has started on lower floors.
- Finish to Finish (FF): B finishes after A finishes.
- Start to Finish (SF): B finishes after A starts. Rare in construction.
Cheat code: If someone asks you to shorten a project, only shortening critical activities helps. Speeding up an activity with float changes nothing.
Project management with MS Project and Primavera is a core Civil Cheatcamp module.
See the Civil CheatcampEnjoyed this article?
Explore more insightful articles and stay updated with our latest content.
View All Articles