Critical Path Method Cheat Sheet: Float, Dependencies and Scheduling Basics

Written by

The Cheat School Team

Published

October 22, 2026

Reading time

2 min read

Every construction schedule in MS Project or Primavera P6 is built on the Critical Path Method. Understand these terms and the software stops being confusing.

Key terms

TermMeaning
ES (early start)Earliest an activity can begin
EF (early finish)ES + duration
LS (late start)Latest it can begin without delaying the project
LF (late finish)Latest it can finish without delaying the project
Total floatLS minus ES (or LF minus EF)
Free floatDelay possible without delaying the next activity
Critical pathChain of activities with zero total float

How to calculate it

  1. List activities, durations and what each depends on.
  2. Forward pass: work left to right to find ES and EF for each activity.
  3. Backward pass: work right to left from the project end to find LF and LS.
  4. Compute float. Activities with zero float form the critical path.

The four dependency types

  • Finish to Start (FS): B starts after A finishes. Example: formwork then concreting. The most common type.
  • Start to Start (SS): B starts after A starts. Example: plastering can start once brickwork has started on lower floors.
  • Finish to Finish (FF): B finishes after A finishes.
  • Start to Finish (SF): B finishes after A starts. Rare in construction.

Cheat code: If someone asks you to shorten a project, only shortening critical activities helps. Speeding up an activity with float changes nothing.

Project management with MS Project and Primavera is a core Civil Cheatcamp module.

See the Civil Cheatcamp

Enjoyed this article?

Explore more insightful articles and stay updated with our latest content.

View All Articles